Construciton of foundation (January 2014)
-1 Floor, Parking (February 2014)
0 Floor, Parking & Building’s Entrance (March 2014)
1st Floor (April 2014)
2nd Floor (May 2014)
3rd Floor (June 2014)
4th Floor (July 2014)
5th Floor (1st half of August 2014)
6th Floor (End of August – 1st half of September 2014)
7th Floor (September 2014)
8th Floor (October 2014)
Construction of Exterior & Interior Walls (November-December 2014)
Making building energy-sufficient + installing windows (January 2015)
Facade + “White Frame” work construction (March-May 2015)
Construction of Foundation (January 2014)
-1 Floor (Parking) February 2014
Ground Floor (Parking) – March 2014
1st Floor (April 2014)
2nd Floor (May 2014)
3rd Floor (June 2014)
4th Floor (July 2014)
5th Floor (July – August 2014)
7th Floor (September 2014)
20th September, 2014
24th September, 2014
8th Floor (October 2014)
Construction of Exterior & Interior Walls (November – December 2014)
13th November, 2014
25th დეკემბერი, 2014
Making our building energy-sufficient + interior work + installing exterior windows (January 2015)
(12th January, 2015)
(27th January, 2015)
Facade + “White Frame” (March 2015)
(26th March, 2015)
(5th May, 2015)
Final touches of facade work (31st May, 2015)